Construction Update

April 21st, 2023

The piling operations for Meadowbrook Health Centre is progressing well. The initial site preparation has been completed, and the piling rig has been brought in to begin the drilling process.

The team is currently drilling the holes and inserting the concrete columns to provide the necessary support for the facility.

The construction team is closely monitoring the progress to ensure that the required number of piles is reached and that the foundation is strong enough to support Meadowbrook Health Centre. Overall, the project is on schedule and moving forward as planned.

Construction Update

March 30th, 2023

Site preparation has begun at Meadowbrook Health Centre this week. Preparing the site for construction is a crucial step that requires careful planning and execution.

The team has commenced working on the piling rig platform. A piling rig platform is a specialised piece of equipment used in the construction industry for drilling deep holes or “piles” into the ground to provide support for large structures.

Construction Update

March 17th, 2023

Today was a momentous day in the construction of Meadowbrook Health Centre. With construction due to begin very soon, the first sod was ceremonially turned onsite at 6-12 Nestor Drive, Meadowbrook.

All three levels of government were in attendance to celebrate the huge milestone for Southern Brisbane and Logan Regions.

Meadowbrook Health Centre is on track for completion in 2024, and will include public and private health services to meet the growing demand in the area.

Construction Update

February 12th, 2023

This week demolition started onsite with the removal of the existing building. This impressive milestone is the very start of construction for Meadowbrook Health Centre and we can’t wait for what’s to come.

The construction of Meadowbrook Health Centre is an exciting and much-needed development for Southern Brisbane and Logan Regions. The centre will house multiple specialisations under one roof, providing patients with comprehensive care and easy access to a range of medical professionals.